Royal Prince Edward Yacht Club
Challenge
- To offset the huge daily electricity cost for the Royal Prince Edward Yacht Club as much as possible.
- To partner with a solar retailer with quality tradesman and extensive experience in the industry in order to satisfy the strict safety and compliance requirements from the Project Managers at the Girvan Group.
-
To implement a sustainable solution able to produce short-term results and secure savings in the decades to come.
Client
Location
160 Wolseley Rd Point Piper NSW 2027 Australia
Why Smart Energy Answers?
- Leading solar provider in Australia
- SEA's Core Values aligning with Royal Prince Edward Yacht Club
- CEC Approved Solar Retailer
- Combined 100 years’ of experience in the solar industry
The Solution
The solar project was carried together with other major renovations for the Club that were managed by the Girvan Group.
SEA worked in conjunction with the Girvan Group observing with the strictest safety and compliance requirements to deliver the best result for the Solar Installation.
About the Installation
- 19.7kW Solar PV system
- 54 x Canadian Solar 365W Perc Monocrystalline panels
- Clenergy Mounting system
- 15kW Sungrow three-phase inverter
- Full Consumption Monitoring with real-time usage and production views
The Result
- The system will help the Club reduce its energy emissions with savings of about $7,000 in the 1st year
NEED MORE INFORMATION?
Book a time with one of our energy experts